Program History
In 2015, Moose Jaw City Council launched the Cast Iron Water Main Replacement Program. Designed to replace 80 kilometres of ageing cast iron water mains over 20 years at an estimated cost of $117 million, it represented the largest infrastructure commitment in Moose Jaw's history.
The program was a significant step forward and was guided by six key principles:
- Replacement of Moose Jaw's cast iron water mains had been deferred for decades.
- Moose Jaw was nearly 20 years behind many Saskatchewan communities in addressing and funding cast iron water main replacement.
- The City needed to take urgent action to address a growing replacement backlog and ensure a reliable, sustainable water distribution system for future generations.
- Moose Jaw had approximately 80 kilometres of cast iron water mains, with some pipes more than 100 years old. Without intervention, ongoing corrosion and deterioration would continue to increase system risks and maintenance costs.
- Cast iron water mains averaged approximately 100 breaks annually, with repair costs reaching roughly $2 million per year.
- Replacing cast iron water mains was identified as the City's highest infrastructure renewal priority.
Program Evolution
Construction under the program began in 2016. Since then, the initiative has evolved from a dedicated cast iron water main replacement program into a comprehensive infrastructure renewal program. In addition to replacing ageing water mains, projects now routinely include upgrades to sanitary and storm sewer systems, sidewalks, and roadways, allowing the City to renew multiple infrastructure assets at the same time while minimizing disruption to residents.
Upon completion of the 2026 construction season, approximately 24.19 kilometres of cast iron water main will have been replaced under the program.
Significantly, the number of annual water main breaks in Moose Jaw has significantly declined as the program has progressed:
2015: 80, 2016: 85, 2017: 116, 2018: 97, 2019: 109, 2020: 53, 2021: 54, 2022: 55, 2023: 27, 2024: 41, 2025: 38


2026 Infrastructure Renewal Program
The 2026 program will include the replacement of approximately 1.9 kilometres of cast iron water main and 1.5 km of feeder main at the following locations:
- Coteau Street from 4th Avenue SW to 2nd Avenue SE
- 1st Avenue SE from Coteau Street E to Lillooet Street E
- 5th Avenue NW from Caribou Street W to Saskatchewan Street W
- Pascoe Drive E from Pascoe Crescent to 13th Avenue NW
- Henleaze Avenue from MacDonald Street to Laurier Street
New for 2026, Infrastructure Renewal work will be delivered by both the City’s Engineering Department and Public Works Department. Historically, this capital project has been managed solely through Engineering; however, beginning this year, Public Works will complete a segment of renewal as part of the City’s broader approach to managing aging underground infrastructure.
Engineering, through contractor PME, will undertake the projects on Coteau Street, 5th Avenue NW, and Pascoe Drive E, while Public Works will deliver the Henleaze Avenue project.
The relevant department will contact impacted property owners about this year’s Infrastructure Renewal Program. This video, featuring Hayley Hart-Rushinko and Travis LeBlanc, provides an overview of planned work, what to expect during construction, and how these upgrades support dependable water service.
As a reminder to residents, sites within each year's program will see milling/paving following a monitoring period while the work is still under its two-year warranty.
Key Information
- Week 29 Infrastructure Renewal Update – 5th Avenue NW to Open Next Week | City of Moose Jaw
- Week 28 Infrastructure Renewal Update | City of Moose Jaw
- Week 27 Infrastructure Renewal Update – Coteau Street E Has Reopened | City of Moose Jaw
- Week 26 Infrastructure Renewal Update – Coteau Street E to Reopen October 21 | City of Moose Jaw
- Week 27 Infrastructure Renewal Update – Coteau Street E Has Reopened | City of Moose Jaw
- Week 26 Infrastructure Renewal Update – Coteau Street E to Reopen October 21 | City of Moose Jaw
- Week 25 Infrastructure Renewal Update | City of Moose Jaw
- Week 24 Infrastructure Renewal Update – 0 Block of Coteau Street W Reopens | City of Moose Jaw
- Week 23 Infrastructure Renewal Update | City of Moose Jaw
- Week 22 Infrastructure Renewal Update | City of Moose Jaw
- Week 21 Infrastructure Renewal Update – 2nd Avenue SE Intersection to Close | City of Moose Jaw
- Week 20 Infrastructure Renewal Update – 5th Avenue NW Work Zone to Extend | City of Moose Jaw
- Week 19 Infrastructure Renewal Update – Part of 5th Avenue NW to Reopen | City of Moose Jaw
- Week 18 Infrastructure Renewal Update | City of Moose Jaw
- Week 17 Infrastructure Renewal Update – MacDonald Street Intersection Temporarily Open | City of Moose Jaw
- Week 16 Infrastructure Renewal Update – Pascoe Drive E Now Open | City of Moose Jaw
- Week 15 Infrastructure Renewal Update – 1st Avenue SE to Close August 3 | City of Moose Jaw
- 2026 Infrastructure Renewal Week 14 Update – 13th Ave NW Reopens to Traffic | City of Moose Jaw
- South Hill Construction Update: Paved Roadways and Infrastructure Renewal | City of Moose Jaw
- 2026 Infrastructure Renewal Week 13 Update/City of Moose Jaw
- 2026 Infrastructure Renewal Week 12 Update | City of Moose Jaw
- Infrastructure Renewal on Henleaze Avenue to Begin July 6 | City of Moose Jaw
- 2026 Infrastructure Renewal Week 11 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Week 10 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Week 9 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Week 8 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Week 7 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Week 6 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Program Week 5 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Program Week 4 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Program Week 3 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Program Week 2 Update | City of Moose Jaw
- 2026 Infrastructure Renewal Program Underway | City of Moose Jaw
- 2026 Infrastructure Renewal Program Begins April 20 | City of Moose Jaw
- 2026 Infrastructure Renewal Program Locations Announced | City of Moose Jaw
- Click here for our interactive map showing current water main infrastructure
Post Construction Paving Approach
The Benefits to Property Owners
With any replacement of the water main distribution lines, properties directly affected benefit through a new water main and water service connection, and perhaps new sewer and pavement, all of which will enhance the value of the property.
Privately-owned land involved in the project would benefit from the local improvement by enhancing the land’s utility and its developmental potential. Because of this, there is an expectation for those who benefit more directly from the new infrastructure to fund a portion of the replacement cost. It is expected that the value for these properties will increase as the service life of the property is extended for an additional 70 years.
In some areas of the City, such infrastructure costs are included in the serviced lot price, and thus these costs have already been incurred by those property owners.
It is important to note that everyone benefits from a renewed water main distribution system. The overall water system will be safer and more secure, and that will benefit the entire city. Specifically, there will be fewer service disruptions, fewer water main breaks, better water quality (less odour and colour) and new, better roads that will not have to be torn up and patched for breaks and leaks.
Project Communication
Since year 1 in 2016, the City has followed a few basic communications practices:
- Send letters to affected property owners in early spring informing them of their inclusion in the project.
- Include information pamphlets explaining the project, what to expect, etc.
- Host an Open House information session for affected property owners, with Project Managers and representatives from City Engineering in attendance to explain the process and answer questions.
In Year 3, further emphasis was placed on project communication to business owners, with those added practices becoming a component of the City’s Communications Policy. Key points include:
- Business owners shall be hand-delivered notices regarding the pending project a minimum of one month from the expected construction start date.
- Once a construction date has been finalized, updated notices shall be delivered a minimum of one week prior.
- Business owners shall be provided with contact information of the Project Manager and Communications Manager to address ongoing questions or concerns.
- The Project Manager and contractor work with businesses to accommodate deliveries.
- Where construction impacts access to area businesses, communications messaging shall indicate that “businesses remain open” throughout the project and, where applicable, maps shall be produced showing how customers may access the respective business(es) during construction.
Weekly updates shall be posted to the City website/social media accounts/local media regarding changes to traffic accommodation plans, project timelines, etc.