Wellesley Park Lift Station Sanitary Force main Installation Begins April 18, 2022

Brendan Fryklund All News, Home Page News

April 13, 2022

MOOSE JAW – The City of Moose Jaw advises that the installation of a sanitary force main for the Wellesley Park Lift Station project will begin Monday, April 18, 2022.

 

The force main will run from the new lift station along Wellesley St. to south of Grandview St. W and Main St. S intersection.

 

The construction area along Wellesley St. will be closed to traffic while the force main installation occurs and is expected to be completed by 5:00 p.m. Friday, April 22, 2022 weather permitting.

 

The contractor will provide access for local traffic to the Wellesley Park and Wakamow Valley area using 1st Ave. SE.

 

The City asks all drivers to obey signage and exercise caution in construction zones for the safety of everyone.