Water Main Replacement Update; 9th Avenue NE and Stadacona St. Intersection Closing For Construction

Craig Hemingway All News, Home Page News, Press Releases

September 24, 2020

Moose Jaw, SK – Water Main Replacement continues and the City of Moose Jaw is pleased to provide the following updates:

Stadacona St. E between 600-1000 blocks: Construction on the 700 and 800 blocks continues, and effective Monday, September 28,  the intersection of 9th Avenue NE and Stadacona St. will be closed temporarily to allow water main replacement to progress. Detours will be in place.

Construction is complete on the 600  block of Stadacona St. E is complete and paving of the 600 block, including the 7th Ave. NE intersection is complete and the road open to traffic.

3rd Ave NW between Oxford St. W and Macdonald St. W: Construction has begun and is progressing north towards Macdonald St. The intersections of 3rd Avenue NW and Hall St. and 3rd Avenue NW and Saskatchewan St. are temporarily closed due to construction. Detours are in place. 

2nd Ave NW between Manitoba St. and Fairford St.: Water main replacement construction is officially complete and the road opened to traffic.

0-300 Blocks High Street West: Water main replacement construction is officially complete and the road opened to traffic.

0-200 blocks Fairford St. E:  Water main replacement construction is officially complete and the road opened to traffic.

Local businesses in the respective construction corridors remain open and we will continue to issue weekly water main construction updates at www.MooseJaw.ca/watermainreplacement and through the City of Moose Jaw app, available for free in your favourite app store. 

The City of Moose Jaw asks all drivers to obey signage and exercise caution in construction zones for the safety of everyone.