MOOSE JAW – Water Main Replacement continues and the City of Moose Jaw is pleased to provide the following updates:

 

3rd Ave NW between Oxford St. W and Macdonald St. W: Paving on the 1000 block is complete. All planned underground work is complete on the 1100 and 1200 blocks. Paving will begin November 4th, 2020 with hopes of completing paving work for the year by the week of November 9th, 2020.

 

600-1000 Blocks Stadacona St. E: Water main replacement construction is officially complete between the 600-900 blocks, including the intersection of 9th Ave. NE. The City of Moose Jaw, in consultation with NIS Contractors Ltd., have made the decision to postpone water main replacement on the 900 block of Stadacona St. E until the start of 2021 construction season. Full completion, including paving, could not be guaranteed by the end of this construction season.

 

0-300 blocks High Street West: Water main replacement construction is officially complete and the road opened to traffic.

 

0-200 blocks Fairford St. E: Water main replacement construction is officially complete and the road opened to traffic.

 

2nd Ave NW between Manitoba St. and Fairford St.: Water main replacement construction is officially complete and the road opened to traffic.

 

Local businesses in the respective construction corridors remain open and we will continue to issue weekly water main construction updates at www.MooseJaw.ca/watermainreplacement and through the City of Moose Jaw app, available for free in your favourite app store.

 

The City of Moose Jaw asks all drivers to obey signage and exercise caution in construction zones for the safety of everyone.