MOOSE JAW – The City of Moose Jaw is pleased to announce that on June 15, water main replacement construction was completed on Saskatchewan St. E from Main St. to 3rd NE. 475m of pvc water line was installed, and 420m of road was rebuilt and paved.
2022 Water Main Replacement construction continues at the following locations:
Grandview St W – 6th Ave SW to 10th Ave SW: 6th Ave SW and 10th Ave SW intersections are open to traffic. 7th, 8th and 9th Ave SW intersections are closed to traffic. Business access to Rodo’s Pizza is available via the south alley.
Ninth Ave SW – Duffield St to Vaughan St.: Both Duffield St and Vaughan St. intersections remain open.
Fairford St E – 3rd Ave NE to 5th Ave NE: Construction and paving is complete and the road has reopened to traffic.
1st Ave NW – Caribou St. W to Hall St W: Oxford St W intersection remains open and the Hall St. W intersection is closed until further notice. Construction has moved south and traffic is restricted from Caribou St. to Oxford St. Beginning Wednesday, June 29, the Oxford St. intersection will be closed to traffic. The intersection of Caribou St. W and 1st Ave NW remains open.
Carleton St – 9th Ave to 10th Ave NW: Paving is complete and the road has reopened to traffic.
Other locations selected for water main replacement in 2022 are:
- Athabasca St E from 2nd Ave NE to 3rd Ave NE
- 2nd Ave NE Athabasca St. E to Hochelaga St. E
- Main St. S from Grandview St. to Home St.
- Grandview St. E from Main St. S to 1st Ave SE
We will continue to issue weekly water main construction updates at: www.MooseJaw.ca/watermainreplacement and through our City of Moose Jaw app, available for free in your favourite app store. The City of Moose Jaw asks all drivers to obey signage and exercise caution in construction zones for the safety of everyone.