Normandy Dr. from VLA Gate to 9th Ave NW Paving Project Begins June 27, 2022

Craig Hemingway All News, Home Page News, Press Releases

June 24, 2022

MOOSE JAW – The City of Moose Jaw advises that a paving project on Normandy Dr. will begin Monday, June 27, 2022.

Crews will pave the road of Normandy Dr. from VLA Gate to 9th Ave NW including all internal intersections. Thatcher Drive and 9th Ave NW intersections are open for traffic. Internal intersections will be affected phase by phase.

Phase 1:         VLA Gate to Corner of Normandy Dr.

Phase 2:         Corner of Normandy Dr to 11th Ave NW.

Phase 3:         11th Ave NW.to East Leg of General Cres

Phase 4:         East Leg of General Cres to East Leg of Marshal Cres.

Phase  5:        East Leg of Marshal Cres to 9th Ave NW

The construction area will be restricted for traffic while paving occurs. The project is expected to be completed by 10:00 p.m. Saturday, July 23, 2022, weather permitting.

Residents/businesses will be required to take alternate routes throughout the duration of the work. Recommended alternate accesses are as follows:

  • Normandy Dr residents: Use 11th Ave NW or 9th Ave NW or VLA Gate.
  • Bingham Rd, Marquis Ave, Admiral/Genera/Marshal Cres residents: Use 11th Ave NW or 9th Ave NW or VLA Gate.
  • Transit detours will be in effect during Phase 3-5 of the project starting the week of July 11th. All bus stops in the VLA neighbourhood will be temporarily out of service, and temporary bus stops will be placed at 11th Ave NW/Thatcher Dr (North side of Thatcher Dr) and 9th Ave NW/Normandy Dr (right turning lane) to accommodate VLA passengers during this closure.

The City asks all drivers to obey signage and exercise caution in construction zones for the safety of everyone. The City thanks residents and visitors for their patience and understanding.