Intersection Upgrades Progressing at Multiple Locations
October 7, 2021
MOOSE JAW – The City of Moose Jaw is pleased to provide an update on intersection upgrades across the City:
9th Avenue NW and Caribou St. (in conjunction with water main replacement):
- Underground work is complete.
- Sidewalk and roadwork is ongoing.
- Traffic loops have been coordinated with surface works.
- Expected completion October 22 (weather permitting).
Thatcher Crossing:
- Medians have been installed.
- Poles are expected to arrive mid-November.
- Electrical work and commissioning to be completed in November after poles arrive.
1st Avenue NW and High St.:
- Poles will arrive mid-November (supplier delay pushed delivery date back).
- Electrical work and commissioning to be completed in November after poles arrive.
- Intersection will function as a four-way stop in the interim.
The City of Moose Jaw asks all drivers to obey posted signage and exercise caution in construction zones for the safety of everyone.