2026 Infrastructure Renewal Program Week 4 Update

hhart-rushinko@moosejaw.caAll News, Home Page News, Press Releases

MOOSE JAW, SK – The City of Moose Jaw advises that the 2026 Infrastructure Renewal Program (including water main replacement) is progressing and has entered its fourth week.

The 2026 program includes the replacement of approximately 1.9 km of cast iron water main and 1.5 km of feeder main at the following locations:

  • Coteau Street from 4th Avenue SW to 2nd Avenue SE
  • 1st Avenue SE from Coteau Street E to Lillooet Street E
  • 5th Avenue NW from Caribou Street W to Saskatchewan Street W
  • Pascoe Drive E from Pascoe Crescent to 13th Avenue NW
  • Henleaze Avenue from MacDonald Street to Laurier Street

Coteau Street W continues to be closed to traffic between 4th Avenue SW and 2nd Avenue SW. The 4th Avenue SW/Coteau Street W intersection is open, but the 3rd Avenue SW/Coteau Street W and 2nd Avenue SW/Coteau Street W intersections are closed.

Transit Stops for Route #4 – Westmount have the following changes:

  • The stop at the southeast corner of Coteau Street W/4thAvenue SW is closed, with passengers asked to use the stop on the southwest corner of Duffield Street W/4th Avenue SW
  • The stop at the southwest corner of Coteau Street W/Tapley Street is closed, with passengers directed to a temporary stop located on the southwest corner of Duffield Street W/Tapley Street (one block south)

The east leg of Pascoe Crescent and Rutherford Street is also currently closed for the 2026 Infrastructure Renewal Program.

Drivers are reminded to obey all temporary traffic signage and exercise caution in construction zones to keep everyone safe. No more #NotoriouslyClose calls.

The City will continue to issue weekly updates as the program progresses. For a full list of the 2026 water main replacement locations, along with full details on the program visit Infrastructure Renewal | City of Moose Jaw.