2026 CIPP Sewer Lining Pre-Cleaning Starts June 15
June 8, 2026
MOOSE JAW, SK – The City of Moose Jaw advises that the City’s contractor is planning to complete pre-cleaning work for the 2026 Cured-In-Place Pipe (CIPP) Sewer Lining Program beginning on June 15, 2026.
No full road closures are anticipated, but there may be lane restrictions on these streets as follows:
| Street | From | To | Expected Start | Expected End |
| 3rd Avenue NE | Athabasca Street E | Fairford Street E | June 15, 2026 | June 26, 2026 |
| Stadacona Street E | 3rd Avenue NE | 4th Avenue NE | June 15, 2026 | June 26, 2026 |
| Dahlia Crescent | Wood Lily Drive | Wood Lily Drive | June 15, 2026 | June 26, 2026 |
| Lillooet Street | 11th Avenue SW | 10th Avenue SW | June 15, 2026 | June 26, 2026 |
| Main Street N | Saskatchewan Street E | Hall Street E | June 15, 2026 | June 26, 2026 |
| 10th Avenue NW | Stadacona Street W | Caribou Street W | June 15, 2026 | June 26, 2026 |
| Hastings Street | 11th Avenue SW | 10th Avenue SW | June 15, 2026 | June 26, 2026 |
| Dogwood Road | Daffodil Drive | Blue Sage Drive | June 15, 2026 | June 26, 2026 |
| Oxford Street W | Henleaze Avenue | Clifton Avenue | June 15, 2026 | June 26, 2026 |
| Coteau Street W | 8th Avenue SW | 4th Avenue SW | June 22, 2026 | July 10, 2026 |
| Fairford Street W | 3rd Avenue NW | Main Street N | June 22, 2026 | July 10, 2026 |
The public is asked to obey all signage and exercise caution in construction zones for the safety of everyone. No more #NotoriouslyCloseCalls.
The 2026 CIPP Sewer Lining Project is expected to run to the end of October 2026, with lining expected to be underway later this summer.