2025 Infrastructure Renewal Program Enters Week 20
September 19, 2025
MOOSE JAW, SK – The City of Moose Jaw advises that Phase 10 of the Infrastructure Renewal Program (including water main replacement) is progressing as the project reaches week 20.
Phase 10 includes the replacement of approximately 1.4 kilometers of cast iron pipe and 700m of feeder main at the following locations:
- Coteau Street W from 8th Avenue SW to 4th Avenue SW
- 6th Avenue SW from Coteau Street W to Grandview Street W
- 4th Avenue SW from Coteau Street W to Duffield Street
- Fairford Street W from Main Street N to 4th Avenue NW
Work continues on Coteau Street W from 4th Avenue SW to 6th Avenue SW. While the 4th Avenue SW and 6th Avenue SW intersections are open, the 5th Avenue SW intersection remains closed.
Westbound stops at Coteau St W & 5th Ave SW and Coteau St W & 4th Ave SW for Transit Route 4 – Westmount remain closed. Passengers are encouraged to continue reading bus stop signage to find the next closest available stop.
Fairford Street W is currently closed for Infrastructure Renewal Program work from 1st Avenue NW to 2nd Avenue NW, and is expected to reopen by Friday, September 26, 2025. The 1st Avenue NW and 2nd Avenue NW intersections are anticipated to remain open.
Drivers are reminded to obey all temporary traffic signage and exercise caution in construction zones to keep everyone safe. No more #NotoriouslyClose calls.
The City will continue to issue weekly updates as the program progresses. For a full list of the 2025 water main replacement locations, along with full details on the program visit moosejaw.ca/watermain-replacement/.