Moose Jaw Residents

Generic filters
Exact matches only
Search in title
Search in content
Search in excerpt
Supporting Moose Jaw's Future Growth

The City of Moose Jaw officially broke ground on the Crescent View Headworks Facility on October 2, 2026. The new facility will replace the existing Crescent View Lift Station, which has served the community since 1961, and will strengthen the City's wastewater infrastructure to support future growth.

The groundbreaking ceremony opened with remarks from Craig Hemingway, the City's Director of Communications, who shared a statement on behalf of the Honourable Buckley Belanger, Secretary of State for Rural Development. Moose Jaw Wakamow MLA Megan Patterson and Mayor James Murdock also delivered remarks, highlighting the importance of collaboration, investment in essential infrastructure and long-term planning for the community.

Residents can follow construction progress and key project milestones on this page, through the free City of Moose Jaw app and on the City's social media channels, including Facebook, Instagram, X, YouTube and LinkedIn.

Watch highlights from the official groundbreaking ceremony.

What is a headworks facility/lift station?

The headworks facility/lift station is the first stop in Moose Jaw's wastewater treatment system. It receives wastewater from all homes and businesses across the city and removes debris, sand, grit, and other materials before it moves on to the City’s Wastewater Treatment Plant for further processing.

By protecting equipment, managing flows, and helping prevent backups during periods of high demand, the facility plays a critical role in maintaining a reliable and efficient wastewater system for the community.

The existing Crescent View Lift Station, a single-storey brick and metal building at the east end of Manitoba Street, built in 1961.
The existing Lift Station facility, located at the very east end of Manitoba St., was built in 1961 and has exceeded its 60-year service life.
Aerial view showing the location of the new Crescent View Headworks Facility, west of the current lift station.
The new facility will be built west of the current lift station, above the regional flood elevation, and is anticipated to be complete by May 2029.
...
Why we need a new facility

In this video, Craig Hemingway provides an overview of why the Crescent View Lift Station is being replaced, how the new Headworks Facility will strengthen this essential service, and how the project will support Moose Jaw’s needs for years to come.

The existing Lift Station facility, located at the very east end of Manitoba St., was built in 1961 and has exceeded its 60-year service life.

Major components of the new facility include:

  • high-efficiency pumps and motors
  • a preliminary wastewater treatment system with fine screening and grit removal
  • a septage receiving station
  • a bulk water fill station
  • two standby generators

The new facility, to be constructed just to the west of the current Lift Station, is anticipated to be completed by Summer of 2029.

The new Crescent View Headworks Facility, once built, will:

  • Accommodate increased flow of wastewater, increasing the city’s ability to support population growth to 45,000 residents (with the possibility of expansion to accommodate up to 60,000), and residential development
  • Be situated above the regional flood elevation to mitigate flood risks
  • Decrease the risk of sewer backups, overflows, and flooding during major storm events
  • Contain mechanical equipment to better capture smaller debris that would otherwise cause premature wear of the pumps
Isometric View Isometric rendering of the new Crescent View Headworks Facility, showing the main building, an elevated structure supported on piles, and adjacent equipment platforms.
Isometric rendering of the new Crescent View Headworks Facility.
...
Funding 

The Crescent View Headworks Facility is one of the largest infrastructure projects in Moose Jaw's history. City Council has approved construction of the facility, which will be funded primarily by the City, with additional support from provincial and federal infrastructure funding.

The City's total budget for this project from 2026-2029 is $73 million.

This project received over $9.7 million from the Building Communities Strong Fund Community Stream (formerly Canada Community-Building Fund). The City thanks the Government of Saskatchewan and the Government of Canada for this funding.

   Funded by:

Project History and Progress
2021
  1. August

    The City engaged AECOM to complete conceptual planning and design for the Crescent View Lift Station. A comprehensive assessment determined that full facility replacement provided the best value.

2022
  1. September

    Completion of 50% detailed design.

  2. December 2022 to June 2023

    Completion of Environmental Site Assessments (Phases I and II) and the Corrective Action Plan.

2023
  1. March

    Completion of 90% detailed design.

  2. Funding applications

    Applications to the ICIP and DMAF funding programs were unsuccessful.

2025
  1. May

    City Council approved a change order to finalize the design for tender.

  2. August

    The City secured $9.75 million through the Canada Community-Building Fund (CCBF), formerly the Gas Tax Fund. Funding will be allocated to construction over five years beginning in 2026.

2026
  1. January

    Seven contractors were prequalified through a Request for Qualifications (RFQ).

  2. February

    Application to the Canada Housing Infrastructure Fund (CHIF) was unsuccessful.

  3. March 24

    City Council approved borrowing $30 million over a 15-year term to fund construction of the Crescent View Headworks Facility.

  4. March 25 to June 2

    Construction tendering period.

  5. July 16

    The City awarded Westridge Construction Ltd. the contract to construct the facility.

  6. October 2

    The City marked the official groundbreaking of the Crescent View Headworks Facility, beginning a new phase in the renewal of its wastewater infrastructure.

© City of Moose Jaw, Saskatchewan. All rights reserved.

Disclaimer: The email addresses and contact forms provided on this website are intended solely for official communication with the City of Moose Jaw. They shall not be used to send unsolicited email messages.