2022 Water Main Replacement Update; 1st Ave NW Construction Underway

Craig HemingwayAll News, Home Page News, Press Releases

June 2, 2022

MOOSE JAW – The City of Moose Jaw advises that construction under the 2022 Water Main Replacement Program continues at the following locations (Transit implications in bold italics):

1st Ave NW – Oxford St W to Saskatchewan St W – Underground work has begun on the 1000 block of 1st Ave NW. Oxford St. W and Saskatchewan St.W intersections are open, 1st Ave/Hall St. W intersection is closed. Local traffic only for residents to access homes Reminder that alley access is for local residents only.

Saskatchewan St E – Main St to 3rd NE – Underground complete, surface work beginning. Both Main St N and 1st Ave NE intersection’s are open to traffic, 2nd Ave NE intersection will remain closed and 3rd Ave NE intersection will remain open. Affects Routes 1 and 2: Stop at Sask St E/Mall Rd out of service.

Grandview St W – 6th Ave SW to 10th Ave SW – Underground works is complete on the 600 block and surface work  is underway. Underground work is ongoing on the 700 block and underway on the 800 block. 6th Ave SW, 7th Ave SW and 8th Ave SW intersections are closed to traffic. The 9th Ave SW intersection is currently open to traffic. Affects Route 4: Stops at Vaugan St/9th Ave, Vaughan St/8th Ave & Vaughan St/7th Ave out of service.

Carleton St – 9th Ave NW to 10th Ave NW – A Public Works project on that block has delayed the start of paving until further notice.

Fairford St E – 3rd Ave NE to 4th Ave NE (Starting June 7th) – Both intersections will remain open. Affects Route 1. 

Caribou St W – 9th Ave NW to 10th Ave NW (2021 Project) – Paving will be complete, and the road reopened to traffic, by end of day Friday, June 3. Affects School Run – Stop at Caribou St W/9th Ave NW out of service.

Other locations selected for water main replacement in 2022 are:

  • Athabasca St E from 2nd Ave NE to 3rd Ave NE
  • 2nd Ave NE Athabasca St. E to Hochelaga St. E
  • 1st Ave NW from Caribou St. W to Laurier St.
  • Main St. S from Grandview St. to Home St.
  • Grandview St. E from Main St. S to 1st Ave SE

We will continue to issue weekly water main construction updates at:  www.MooseJaw.ca/watermainreplacement and through our City of Moose Jaw app, available for free in your favourite app store.  The City of Moose Jaw asks all drivers to obey signage and exercise caution in construction zones for the safety of everyone.